GU ELECTRIC — Beyond the CabinetGU ELECTRIC — Beyond the Cabinet Get a quote
B U I L D T O D R A W I N G PCC power center cabinet · Photo 01
PRODUCT — 02 · Low-Voltage Distribution & Assemblies

PCC power control center

Main gate for high-current incoming feeders
Model GU-PCC · AC 400V · Air circuit breaker ≤4000 A · MOQ 1 unit
The PCC Power Control Center Cabinet handles the main incoming and primary distribution of a low-voltage system section: a drawout air circuit breaker serves as the main switch, rated up to 4000 A, feeding downstream outgoing cabinet groups (GGD / GCS) to form the distribution section. The drawout main switch has interlocks and visible isolation for maintenance; incoming, bus tie, and outgoing cabinets assemble in the same module, with factory-prefabricated through-busbars. It is the first stop on the transformer's low-voltage side, and the cabinet's short-time withstand and temperature rise are strictly matched to the main switch's breaking capacity.
  • Main switch: drawout air circuit breaker (ACB) ≤4000 A, breaking capacity matched to system short-circuit capacity
  • Cabinet: same module as GGD / GCS for section assembly, factory-prefabricated through-busbars
  • Bus tie scheme: two busbar sections mutually backed up via bus tie cabinet, auto-transfer or manual on loss of power
  • Monitoring: three-phase current/voltage, power, and energy full-parameter meter, RS485 reporting
  • Short-time withstand: Icw matched to main switch (up to 80 kA), temperature rise ≤70 K
≤4000 AAir circuit breaker
DrawoutMain switch drawable
80 kAShort-time withstand (matched)
1 unitMOQ 1 unit · ≥5 recommended for volume production
01 — SPECIFICATION

Specifications

The table below covers 80% of factory distribution room cases. Anything outside it we can still build — those are engineered items, quoted separately, with an indicative price the same day.

TypePCC floor-standing incoming / bus tie cabinet, assembled in the same section as GGD / GCS
Standard sizes (W×D×H)1000×800(1000)×2200 mm (incoming cabinet), custom build available
Enclosure constructionProfile frame, busbar compartment / breaker compartment / cable compartment separated
Main switch typeDrawout air circuit breaker, rack in / rack out mechanism with interlocks
IP ratingIP30 / IP42 (electrical room)
Cable entryTransformer-side busbar / large cable bottom entry, feeder busbar continuous through
Rated voltageAC 400V, 50 Hz
Main incoming deviceDrawout air circuit breaker 630–4000 A
Short-time withstand current, Icw50 / 65 / 80 kA (matched to the main breaker interrupting capacity)
Main busbarTMY tinned copper busbar sized by current, torqued to 30–40 N·m with mark-off lines
Bus tie configurationTwo busbar sections cross-fed through a bus tie cabinet, automatic transfer (with protection interlock) or manual
Protection configurationAir circuit breaker with smart trip unit (LSIG: long-time / short-time / instantaneous / ground)
MonitoringFull-parameter meter (U/I/P/Q/cosφ/energy), RS485 / Modbus reporting
Component brandsSchneider / ABB / Siemens air circuit breakers, customer-specified brands supported
Single-transformer incoming typeOne transformer per busbar section, PCC incoming + GGD/GCS feeders
Dual-transformer bus tie typeTwo busbar sections + bus tie cabinet cross-feed, automatic transfer on loss of supply or manual paralleling
Combined incoming + metering typeMetering integrated in the incoming cabinet (utility-side gateway meter per local requirements)
Drawout feeder typeFeeders in the PCC section also drawout (mixed with GCS)
Retrofit / breaker replacement typeReplace air circuit breakers and protection in existing PCC cabinets, busbar reuse assessed
Assembly standardGB/T 7251.1 / IEC 61439-1, main circuit verified to type-test criteria
Interlock verificationDrawout mechanism rack-in/rack-out interlock, position signals verified cabinet by cabinet
Busbar testingTorque mark-off lines + busbar temperature rise calculation (≤70 K)
Routine tests (every unit)Insulation resistance, withstand voltage 2500V/1min, trip unit operating characteristics
Documents with shipmentSingle-line diagram, protection setting table, busbar specification, BOM, test report
02 — CONFIGURATOR

Five steps to specify your run

A configuration summary is generated as you go. It travels with your inquiry, saving a round of confirmation.

01Main breaker current
02System configuration
03Section-coupled cabinet type
04Protection configuration
05Options (multiple)
03 — CRAFT

Build details

Systems have been in service for decades, and the failure points are always the same few: poor busbar contact, water ingress at the door seal, high temperature rise in the correction cabinet, and mis-phased outgoing feeders. The six hard rules below are written for exactly these points — every cabinet can be traced to them.

Torque mark line

Busbar torque fastening, re-checkable

Main busbar torqued to 30–40 N·m and marked point by point: during inspection, a glance at the line shows whether anything has loosened. On high-current cabinets the contact surface is the critical point — we do not skip this step.

Temperature rise calculation

Full-load based, not rule of thumb

The 4000 A busbar is calculated for temperature rise at full load (≤70 K), and the busbar datasheet ships with the cabinet. High-current cabinets cannot tolerate "close enough" — a small margin shortfall means a trip on a hot summer day.

Trip setting

LSIG tested unit by unit

The electronic trip unit's long-time / short-time / instantaneous / ground fault four-stage protection is tested for operating characteristics on every unit, and the settings are recorded in the setting table — this is what makes upstream/downstream coordination work.

Rack-in interlock

Cannot rack in while energized

Drawout mechanism position interlock: the door cannot be opened in the connected position, and maintenance is only possible in the test position. Operator safety on high-current cabinets depends entirely on the mechanism — verified unit by unit.

Bus tie interlock

No risk when paralleling buses

Bus tie auto-transfer is equipped with a protection interlock (buses may only be paralleled when both sections are healthy), preventing a faulted bus from being paralleled to a healthy bus — reliability design always takes priority over automation.

Continuous run pre-assembled

Assembled as a full section at the factory

Assembled in the same factory as the feeder cabinets: continuous busbar, full-section dielectric test, unified nameplate — on site it is lifted into place, connected, and energized. This is work that cannot be done when sourcing sections separately.

04 — EVIDENCE

Photos & enclosure construction

Below are photos taken in our own shop — from the complete unit down to the internal busbars and secondary wiring. Every build detail can be checked item by item.

PCC power center cabinet · Photo 01
Stainless Steel Double-Door Weatherproof Control Cabinet · Photo 01
PCC power center cabinet · Photo 02
Stainless Steel Double-Door Weatherproof Control Cabinet · Photo 02
PCC power center cabinet · Photo 03
Stainless steel VFD panel · Photo 03
FRONT VIEW Power meter Status indication Channel base at the bottom · inter-cabinet busbars run through H 2200 W 800 / 1000 / 1200 IP54 standard IP65 optional Ue 400V ≤2000A Icw 30–65kA
Verifiable build checklist:2.0 mm seam-welded enclosure · diagonal ≤1.5 mm · busbar torqued to 30-40 N·m with witness marks · busbar joint temperature rise ≤70 K · segregated wiring compartments · CTs and meters in separate compartments · 60-80 μm coating · 2500 V/1 min withstand on every unit.

Image key: 01–05 are shop photos (the numbers match the shot list). The line drawing shows the front elevation of the enclosure; dimensions match the specification table above.

05 — APPLICATIONS

Where these cabinets go

These are the routine applications — we can talk scheme and configuration directly. For the industry view, see the industry pages.

Factory main distribution room

First stop on the transformer secondary — the backbone of the whole lineup.

Large workshop substation

Multiple busbar sections + bus tie for mutual backup.

Data Centers / Server Rooms

Dual-source PCC sections + row-level panelboard system.

Commercial complexes

Center distribution with multiple transformers split into sections.

Municipal pump stations / water treatment plants

High-capacity incoming lines and distribution to critical loads.

Section retrofit

Replace PCC incoming cabinet + protection upgrade, with busbar reuse assessment.

06 — TERMS

Commercial terms

Specification dated September 2026; quotations follow this.

Drawings & designFree
MOQ1 unit (5 or more recommended for production)
Production lead time15-25 days after drawing approval
on-time delivery98%
Warranty12 months
Loading portNingbo / Shanghai, China
Component brandsSchneider / ABB / Siemens / Chint
Factory visit & dispatch confirmationFactory visits welcome; finished-cabinet photos and video before dispatch
Capacity5,800+ units / year
07 — DOWNLOADS

Documents for your engineering team

Selection manual, outline dimensions and RFQ checklist — for the customer's electrical engineer. All three documents are being organized by product line; download links go live once complete.

PDFSelection and configuration manualTechnical highlights, specifications, typical solutions and commercial termsIn progress · pending
DXFCommon outline & cut-out dimensionsFront view / side view / foundation and cable entry cutoutsIn progress · pending
XLSRFQ data checklistInformation to confirm before quoting — fill in and send backIn progress · pending
08 — FAQ

Six questions procurement and electrical engineers ask most

What is the difference between PCC and MCC?

PCC (Power Control Center) handles the incoming side: high-current incoming lines and busbar distribution. MCC (Motor Control Center) handles the outgoing side: centralized control of motor circuits (drawer units). A single electrical room is often a combination of PCC incoming + MCC / GCS feeders — we build both ends and assemble the sections in-house.

Why drawout for air circuit breakers?

Drawout (rack in / rack out): breakers can be serviced or replaced without dismantling the busbars — rack it out and swap it, with interlocks to prevent live operation. Fixed-type is cheaper, but replacing a breaker means a shutdown and busbar teardown. For incoming cabinets — positions that move maybe a few times a year but matter enormously when they do — drawout is worth it.

Do two transformers always need a bus tie?

Not always, but if mutual backup is required, we recommend it: when one section loses power, the bus tie closes (manual or auto-transfer with blocking), keeping critical loads energized. Auto-transfer on the bus tie must include protection blocking and synchronization conditions — we issue the settings as part of the system design, never a bare transfer.

What if the load exceeds 4000 A?

4000 A is already the common upper limit for low-voltage cabinets. Beyond that, two paths: split transformer operation (two sections at 4000 A class each), or busway risers + floor-level distribution cabinets. Send us the transformer capacity and load distribution, and we will recommend the sectioning.

Is arc flash protection necessary?

It is standard on medium voltage switchgear. For high-current low-voltage PCC sections (above 2500 A, unattended), we recommend arc flash sensors + fast tripping: arc faults are cleared from inception to trip in tens of milliseconds — an order of magnitude difference in personnel and equipment damage. On a tight budget, at minimum reserve the interfaces.

What can intelligent monitoring show?

Full electrical parameters (three-phase U/I/P/Q/cosφ/energy) + breaker status + trip unit event logs, reported via RS485/Modbus to power monitoring or the BA system; busbar temperature sensing is optional. Operations can see the health of the entire section from the control room — inspections are no longer done blind.

09 — RELATED

Other cabinet types in the same main circuit

Related products use color-block placeholders for now (product photos not yet complete; they will be replaced together). Internal links will be filled in once live URLs are confirmed.

10 — RFQ

Send us the system diagram — we will deliver the full section design together

Send us your single-line diagram or transformer capacity for a free PCC incoming and full-section distribution design · Quotation within 24 hours. Direct from the source factory, MOQ 1 unit, 15–25 day delivery, 1-year warranty.

Email your inquiry WhatsApp: +86 186 5712 0011
GU ELECTRIC (Zhejiang Golden Unicorn) · 5,000 sqm workshop, Fengchuan Industrial Zone, Tonglu · 20 people · 5,800+ units per year
ISO 9001:2015 · CE(LVD+EMC) · CQC · IP65

When you write, include: single-line diagram or primary scheme, switch room layout, load list, and component brand requirements. You do not need complete drawings — capacity and cabinet type are enough to start.

PCC Power Control Center Cabinet · MOQ 1 unit · 15–25 days Get a quote