HomeTechnical notes › How to Read a Solar Combiner Box Wiring Diagram: PV+/PV-, SPD and Monitoring Wiring in One Primary and One Secondary Diagram

05 Informational content / Technical articles 2026-09-11 Published ~ 11 min read GB/T 18479

How to Read a Solar Combiner Box Wiring Diagram: PV+/PV-, SPD and Monitoring Wiring
Primary and Secondary Diagram Reading

A combiner box wiring diagram reads in two halves: the DC primary circuit and the secondary monitoring circuit: one half runs PV+/PV- through the fuses to the output; the other covers the auxiliary wiring for the SPD and the monitoring module. This article follows GB/T 18479 to set out the reading sequence for the diagram and the key wiring points for polarity, surge protection and monitoring. Zhejiang Golden Unicorn buildscombiner box enclosures, and ships each unit with a cutout drawing and an enclosure inspection record, ISO 9001:2015 certified,MOQ 1 unit · 15–25 days.

1. DC Primary Circuit Path (PV+ → Fuse → Combiner → Output)

Read the diagram left to right (or bottom to top):

  1. Input: N strings, each PV+ and PV- passing through its own gPV fuse (two-pole protection);
  2. Busbar: the outputs of all fuses combine onto the PV+/PV- copper busbars;
  3. main breaker: DC load-break switch / DC circuit breaker (for isolation, rated voltage ≥ system voltage);
  4. Output: routed through a waterproof cable gland to the DC side of the inverter.
SCHEMATICBusbarsTerminal blocksMain circuit breakerControl & protection devicesTerminal block outgoing cables
Figure — 1. DC Primary Circuit PathCabinet structure diagram · photo pending

2. Polarity and Color Coding (Red Positive, Black Negative)

PolarityConductor / Busbar ColorTerminal Marking
PV+Red (or brown)DC+ / PV+
PV−Black (or blue)DC− / PV−
PEYellow-greenPE

DC polarityReversed connection burns the fuse at best, destroys equipment at worst— check the polarity markings on the diagram first, then verify with a multimeter before energizing.

3. Surge Protective Device (SPD) Wiring (ground discharge)

4. Monitoring Module Wiring (secondary circuit)

Monitoring module wiring falls into four groups: ① each string'sHall sensor / shuntsamples string current; ② busbar voltage sampling; ③ RS485 communication(A/B twisted pair with shielded ground, to the inverter / monitoring system); ④ auxiliary power(typically DC 24V or AC 220V). When reading the drawing, noteseparate routing for power and signal cablesand single-end grounding of the 485 shield — cable specs and shielding requirements are called out on the drawing.

SCHEMATICBusbarsTerminal blocksMain circuit breakerControl & protection devicesTerminal block outgoing cables
Figure — 4. Monitoring Module WiringCabinet structure diagram · photo pending

5. Five Wiring Practice Points (construction acceptance)

Method

Torque: tighten fuse holders and busbar bolts to the torque table and mark with a line; ② Crimp: match cold-pressed cable lugs to conductor size; tinning before crimping is prohibited; ③ Firestop sealing: seal cable entry holes with both waterproof firestop putty and firestop sealant; ④ Wire sequence: tag each input per the drawing number (PV1+ / PV1− …) and match it one-to-one with the monitoring module channel; ⑤ Re-check: before energizing, verify polarity with a multimeter and insulation resistance ≥ 1MΩ (1000V megohmmeter).

FAQ FAQ

Do both the positive and negative poles of a combiner box need fuses?

We recommend fuses on both poles. DC fault current has no natural zero crossing, so two-pole fusing improves breaking reliability (follow the design drawing for the specific configuration).

Should the SPD go before or after the main switch?

Typically installed atthe downstream side (near the output), per the drawing; either way, the run from the SPD to the PE bar must be as short as possible.

What cable should be used for the RS-485 communication line?

Shielded twisted pair (e.g., RVSP 2×0.75), with the shieldgrounded at one end only, routed in a separate tray from power cables.

Does the solar combiner box require an insulation test?

Yes. Before energizing, use a 1000V megohmmeter to measureDC circuit-to-ground insulation ≥ 1MΩ. Do not perform the test in rainy weather.

Related pages:Technical notes · Products · Industries · Resource center · FAQ · Get a quote

Related reading

Need Distribution box, distribution cabinet? Build to drawing · MOQ 1 unit · 15–25 day delivery

A source factory in Zhejiang (Fengchuan Industrial Zone, Tonglu — 5,000 sqm, a team of 20, 5,800+ units a year), holding ISO 9001:2015 / CE(LVD+EMC) / IP65 test report. Build-to-drawing service for distribution boxes, low-voltage assemblies, PLC control cabinets and VFD panels. Free drawing review, photo/video inspection before shipment.