HomeTechnical notes › Equipotential Bonding Terminal Box Installation: Location, Height & Connection Requirements

05 Informational content / Technical articles 2026-09-11 Published ~ 11 min read GB 50303

Equipotential Bonding Terminal Box Installation
Location, Height & Connection Requirements

Wrong location, undersized bonding conductors, wrong wire color — and the whole installation fails inspection. This article follows GB 50303 The 5 code requirements for equipotential bonding terminal box installation, broken down, with an inspection checklist. Zhejiang Golden Unicorn produces 10,000+ equipotential boxes per year,ISO 9001:2015 · MOQ 1 unit.

1. Installation Location Requirements (GB 50303)

GB 50303 Location requirements for the equipotential bonding terminal box:

  1. The MEB is installed at thepower supply incoming point(electrical room or floor distribution room), close to the PE bar.
  2. The LEB is installed inWithin the local zone(e.g., inside a bathroom wall), at the point closest to that zone's metal piping.
  3. Do not install inlocations exposed to direct water spray(e.g., directly below a shower head).
  4. The location must remain accessible for maintenance; do not seal the box inside a non-removable decorative layer.
SCHEMATICBusbarsTerminal blocksMain circuit breakerControl & protection devicesTerminal block outgoing cables
Figure — 1. Installation Location RequirementsCabinet structure diagram · photo pending

2. Installation Height (MEB vs LEB)

TypeMounting heightMethodNotes
MEBBottom edge 0.5–1.5 m above floorSurface-mounted / flush-mountedInside electrical room
LEBBottom edge 0.3–0.5 m above floorPrimarily flush-mountedBathrooms / machine rooms
LEB (machine room)Bottom edge 0.3 m above floorFlush mountBelow raised access floor

3. Bonding Conductor Cross-Section (GB 50057)

Cross-section

GB 50057 Requirements:
① MEB to ground electrode:copper ≥ 25 mm² or copper busbar 25×4
② MEB to each pipe:Copper ≥ 6mm²
③ LEB to each pipe/equipment:Copper ≥ 6mm²
④ LEB to MEB:Copper ≥ 16mm²
⑤ Conductor color:Yellow-green striped

SCHEMATICBusbarsTerminal blocksMain circuit breakerControl & protection devicesTerminal block outgoing cables
Figure — 3. Cross-Section of Bonding ConductorsCabinet structure diagram · photo pending

4. Connection Methods (3 Types)

Connection MethodsApplicationConductor Size
Bolted compression connectionCopper busbar / copper terminals≥ 6mm²
Exothermic weldingCopper-to-copper / copper-to-steel≥ 16mm²
Cable lug compressionConductor to copper busbar≥ 6mm²

5. Acceptance Checklist (6 mandatory checks)

  1. Location: MEB at the incoming supply, LEB within the local area
  2. Height: MEB 0.5–1.5 m, LEB 0.3–0.5 m
  3. Connect: All metal pipes, equipment and rebar are bonded
  4. Cross-section: Conductor cross-sections meet GB 50057 requirements
  5. Color: Conductors are green/yellow two-color
  6. Continuity: LEB is connected to MEB; continuity test passed

FAQ FAQ

At what height is the equipotential bonding terminal box installed?

MEB: bottom edge 0.5–1.5 m above floor; LEB: bottom edge 0.3–0.5 m above floor. Do not install where it is directly exposed to water spray.

What color are equipotential bonding conductors?

Yellow-green striped(standard PE color), matching the equipment grounding conductor.

What is the cross-section of the LEB-to-MEB bonding conductor?

≥ 16mm² copper(BVR-16mm²); do not substitute a smaller cross-section.

Can the equipotential bonding terminal box be surface-mounted?

The MEB may be surface-mounted in the electrical room; the LEB is generally flush-mounted inside bathroom walls, since surface mounting affects appearance.

Related pages:Technical notes · Products · Industries · Resource center · FAQ · Get a quote

Related reading

Need Distribution box, distribution cabinet? Build to drawing · MOQ 1 unit · 15–25 day delivery

A source factory in Zhejiang (Fengchuan Industrial Zone, Tonglu — 5,000 sqm, a team of 20, 5,800+ units a year), holding ISO 9001:2015 / CE(LVD+EMC) / IP65 test report. Build-to-drawing service for distribution boxes, low-voltage assemblies, PLC control cabinets and VFD panels. Free drawing review, photo/video inspection before shipment.